Town council pursues federal funds for STP, Hospital Way

Application about planning for future, says mayor

  • November 18 2026
  • By Corey LeBlanc    

ANTIGONISH – After discussions over multiple meetings, council for the Town of Antigonish has decided to apply for provincial and federal funding to help finance a pair of big-ticket infrastructure initiatives.

During a special meeting on Nov. 12 – one day before the second-stage submission deadline – council approved a motion to direct town staff to update and submit the 2025 Northern Collector Canada Housing Infrastructure Fund (CHIF) application to the Nova Scotia Provincial CHIF stream for up to $29.7 million in eligible costs.

In a follow-up email interview with The Journal, Mayor Sean Cameron said making the application is “about planning for Antigonish’s future.”

He explained that the application has two parts: expanding the sewer treatment plant (STP) to support housing and growth for the next 30 years, and building the water and sewer infrastructure needed to service Hospital Way as a secondary access route to Antigonish Memorial Regional Hospital.

“Not only will this support future development, but it will also provide residents with a more reliable route to the hospital, particularly during flooding events. It’s an investment that benefits both current and future generations,” Cameron added.

He pointed out the Bay Street construction project last year “highlighted a major concern that people would argue should have been addressed years ago; the need for a second route to our regional hospital. Hospital Way gives us the opportunity to address that need while also supporting future housing growth.”

Noting it is one of the biggest capital investments the town has ever considered, Cameron said, “It’s not a decision we take lightly.”

He added, “If we’re successful in securing this funding and moving the project forward, Hospital Way would become our focus from 2027 to 2031, and many other capital projects would need to be put on hold.

“But, when we look at the opportunity in front of us, it’s an investment worth serious consideration. When we look ahead to where Antigonish will be in 10, 20, or 30 years, this is the kind of project we need to be planning for now. This is about planning for the future.”

As spelled out in the approved town council motion, “The Town acknowledges and accepts that, if the application is approved the eligible costs, up to the submitted and approved estimate, may be funded up to 40 per cent federally, 33.33 per cent provincially, and the balance of eligible costs, including those exceeding the approved estimate and all ineligible costs, will be the responsibility of the Town.”

If this CHIF application is approved, the federal and provincial contribution would cover 73.33 per cent of the price tag, or $29,676,010, including $15,212,927.60 for the STP and $14,463,082.40 for Hospital Way.

When it comes to the emergency access road, costs not eligible for CHIF funding – such as paving – would cost an estimated $2,755,041.25.

Along with providing secondary access to the regional hospital, the proposed roadway would give the opportunity to carry out development on town-owned land.

As part of the information-gathering process, Mayor Cameron sent a letter to Warden Nicholas MacInnis of the neighbouring Municipality of the County of Antigonish outlining the CHIF application, while gauging the potential financial commitment it would make to the proposed Hospital Way initiative.

In a Nov. 10 email to Mayor Cameron and CAO Randy Delorey, Shirlyn Donovan – county CAO – indicated that, at a special meeting on Nov. 9, council approved a motion to support the town’s funding application to the CHIF by committing financial support for one-third of the unfunded portion of the STP upgrades, as per the town and county’s intermunicipal service agreement.

That commitment from the county is for $1,352,429.26.

  

County won’t commit to supporting Hospital Way

“There was discussion on the added request for the municipality to commit financial support for 50 per cent of the unfunded portion of the construction of Hospital Way,” Donovan wrote in the email. “Council was not willing to proceed with this financial support as proposed, but are interested in collaborating on an emergency (gravel) road and want to ensure that all interested parties, including Nova Scotia Health, landowners and other municipalities serviced by the regional hospital are included in the discussion.”

She added, “We look forward to future discussion.”

When asked for further comment, the county provided The Journal with a statement from Warden Nicholas MacInnis, in which he reiterated the municipality’s support of the STP expansion, “in keeping with our commitments under the inter-municipal agreement.”

He added, “With respect to the Hospital Way proposal, the County recognizes the importance of establishing a secondary emergency access route to the Antigonish Memorial Regional Hospital. Ensuring reliable access for emergency vehicles is critical to the safety of patients, staff, and the broader community. County Council remains open to further discussions on this proposal.”

As part of the CHIF application, if approved and moves forward, even with the county’s commitment to the STP, the town would be responsible for an expected $6,562,162.60 in eligible costs, including $2,704,858.53 for the STP and $3,857,304.08 for Hospital Way.

And, at this point, with no other commitments to contribute, the town would also be responsible for an expected $2,755,041.25 in costs for Hospital Way that would not be covered by an approved CHIF application.

The expected project cost to the town, with the CHIF funding, would be $9,317,203.85.

During the town council’s special meeting, Kyle Meisner – director of infrastructure and engineering – made a presentation on the proposed CHIF application, including – if approved – how it would impact the municipality’s five-year capital plan.

As for the STP back-end and capacity work, the impact would be $150,241 in the 2027-28 fiscal year and $2,554,617 in 2028-29. With the Hospital Way portion of the effort, it would be $884,251 in 2029-30 and $5,728,094 in 2030-31.

“We have to somehow make this happen,” Coun. Jack Sullivan said during council’s discussion at the special meeting leading up to the motion, stressing the importance of trying to take advantage of these available provincial and federal monies.

Describing it as a “great opportunity,” Mayor Sean Cameron noted he was “disappointed” by the county’s response, adding the town is “too small” to handle the costs “all on our own.”

Couns. Diane Roberts and Juanita Pelly echoed that feeling, even though – as Pelly noted – “I know it is a big ask.”

Deputy Mayor Andrew Murray said he was “not totally surprised” by the county’s response.

If council decided to make a submission to the second phase of the application process by the deadline on the following day (Nov. 13), he asked if there was time for the town to give the idea more consideration before having to sign on the dotted line for an approved agreement.

Delorey indicated that the town had not been provided with any information on a response timeline, offering it could be one month or it could be six months. He later explained – whether approved or rejected – the proposed agreement would be returned to council for guidance and a decision, describing that as the possible “off ramp” for pulling out.

Regarding concerns about the potential strain on the town, if it has to take on all of the municipal financial commitment involved with an approved CHIF application, CAO Delorey explained that applying does not mean they are making a “formal commitment,” explaining the terms of any agreement – such as the potential to return monies – would be determined as part of a finalized document. He noted that clauses in similar agreements spell out that monies would have to be returned if projects are not completed.

Pelly asked if maintaining a potential gravel emergency road – an alternative to Hospital Way – would be as or even more expensive.

Coun. Leon MacLellan told his council colleagues that he needed “more information on the impact on other projects,” if they make the commitment involved with the CHIF application, if it is successful. He questioned if it would “suck up capital funding” and delay other initiatives, such as planned work on Hawthorne Street.

“It is easy to get gung-ho, but we are responsible for all the rest, too,” he added, when it comes to infrastructure projects, offering the challenge for a “small town to fund this alone.”

Even with the potential of tapping into 73.3 per cent of funding for the projects, MacLellan said he was “not convinced we can afford it.”

  

Others need to step up

Sullivan, like many of his colleagues, reiterated the argument offered during previous council discussions that the town should not be solely responsible for the municipal piece of the pie, considering the proposed Hospital Way would benefit municipalities in the region that access Antigonish Memorial Regional Hospital.

“Why is the burden falling on us?” he asked, while offering his optimism that the county “will step up” and make a financial commitment to constructing Hospital Way, if the CHIF application is approved.

Roberts added the town “should be talking to other municipalities” regarding contributing to paying for the roadway.

At that point, MacLellan suggested – considering the conversation had veered into discussion of negotiations and strategy – the meeting should go in camera.

After spending approximately 20 minutes in camera, council returned to the special meeting and approved the motion to move forward with the next stage of the CHIF application process.